City planning November 25, 2026 · Highway 4 · Road money

Texas estimates July 1, 2027 bids and a $173.7 million cost for the Highway 4 widening to Starbase

Gateway to Mars card: Highway 4 widening. $173.7M estimate. State's estimated bid date: July 1, 2027. An aerial of the flats west of Starbase with part of Highway 4 drawn in blue, with a Texas locator in the corner
Aerial: USDA NAIP, June 2022, public domain. Road line: TxDOT. The line shows part of the highway.

The Texas Department of Transportation lists July 1, 2027 as the estimated date to take bids on rebuilding and widening Highway 4 from two lanes to a divided four-lane road, its project list shows. The project runs from FM 1419 (Oklahoma Avenue) to LBJ Boulevard at Starbase. The list's estimate is $173,722,953.90.

  • The date is an estimate: TxDOT defines it as the date a district anticipates a project going to bid. The row shows no approved or actual bid date.
  • The dollars are an estimate too: TxDOT defines the figure as the most recent assumed cost of construction.
  • How long: up to 1,035 working days. The list gives no construction start date.
  • Where it stands: status active, stage "PS&E" (plans, specifications and estimates).

Other dates in print: TxDOT's project page still says summer 2026 was the earliest the project would be ready for bids, and calls that timeline approximate. KRGV reported on Aug. 28, 2026 that bids would come in the fall of 2027 and the work could take about two and a half to three years. July 1, 2027 falls inside the state's fiscal 2027, which ends Aug. 31, 2027. Fiscal 2027 is the year the City of Brownsville gave in August (our Sept. 12, 2026 story).

About the $192.4 million: that is the construction cost estimate for this project in TxDOT's 2027 Unified Transportation Program, which lists the same amount in authorized funding. The project list's estimate is about $18.7 million lower, and the list does not explain the difference.

What's planned: TxDOT's page describes improvements along about 14 miles: two 12-foot concrete lanes added from about 2,700 feet east of Oklahoma Avenue to Joanna Street, 8-foot paved shoulders, and a 3.75-mile bike path from Quicksilver Avenue to LBJ Boulevard, all within the existing right of way.

Also on the list for Cameron County:

  • "Port of Brownsville SH 48 Texas LNG": $16,000,000, estimated bids Feb. 2, 2027. The Brownsville Navigation District is the local agency. Stage: planning.
  • Highway 4 drainage ditch bridge replacement: $3,722,501.12, estimated bids Dec. 1, 2027.
  • East Loop, I-69E to Highway 4: $169,138,092.82, estimated bids May 2, 2030. The Cameron County Regional Mobility Authority is the local agency.

Next: Starbase's request for proposals for an AI app platform, RFP 26-04, takes questions through Monday, Nov. 30, 2026 and proposals through Monday, Dec. 7, 2026 (our story). FAA comments on the Starbase launch review also close Dec. 7 (our Nov. 23, 2026 story). Starbase's City Commission holds its SpaceX tax abatement hearing at 7 p.m. CT Wednesday, Dec. 9, 2026 (our Nov. 22, 2026 story).

Around the world

China's Shenzhou-24 has docked with the Tiangong space station, Xinhua reports. It lifted off at 7:18 p.m. ET (6:18 p.m. CT) Tuesday, Nov. 24, 2026, the China Manned Space Agency says.

SpaceX says Falcon 9 launched USSF-266 at 11:08 a.m. ET (10:08 a.m. CT) Tuesday, Nov. 24, 2026, from Vandenberg.

NASA says a Progress cargo ship is scheduled to dock with the International Space Station at 7:11 a.m. ET (6:11 a.m. CT) Thursday, Nov. 26, 2026.

Sources: TxDOT, Project Information, project 0039-10-091, read Nov. 25, 2026 · TxDOT, SH 4 Boca Chica Blvd. widening · KRGV, Aug. 28, 2026 · TxDOT 2027 Unified Transportation Program · NASA